The history of the company began with the idea of building the company capable of producing the connecting parts of pipelines the feature of which will be improved reliability, quality, and speed of production.

2011
The design contract was signed with a leading industry institute, which in a short time prepared the engineering design documentation for construction.

2013
Started construction of the administration and on-site building for plant, boiler house, auxiliary buildings and grounds.

2014
Started construction of an industrial building.

#
#
#

2015
Mounting of the main equipment in the production casing is underway .

#